TM 9-2320-366-20-5
20-66. LIGHT MATERIAL HANDLING CRANE (LMHC) TURRET REPLACEMENT
This task covers:
a. Removal
c. Follow-On Maintenance
b. Installation
INITIAL SETUP
Equipment Conditions
Personnel Required
Engine shut down (TM 9-2320-366-10-1).
(2)
LMHC power cable removed (TM 9-2320-366-10-1).
LMHC remote control cable removed (TM 9-2320-366-
10-1).
a. Removal.
WARNING
Light Material Handling Crane (LMHC)
boom assembly weighs approximately 150
lbs (68 kgs). Use an assistant when
removing boom assembly. Failure to
comply may result in injury to personnel.
NOTE
Steps (1) and (2) require the aid of an
assistant.
(1) Remove quick release pin (1) from turret (2).
(2) Remove boom assembly (3) from turret (2).
(3) Remove quick release pin (4) from turret (2).
(4) Remove turret (2) from mast (5).