20-81. DIGITIZATION KIT POWER CABLE REMOVAL/INSTALLATION (CONT)
(30) Connect terminal lug TL14 (61) to terminal block
TB2 connector 43 (62).
(31) Install terminal lug TL21 (63) on ground stud (64) with
washer (65), lockwasher (66), and nut (67).
c. Follow-on Maintenance
(1) Install power distribution panel (para 16-2).
(2) Install kick panel (para 16-3)
(3) Connect batteries (para 7-57).
(4) Operate equipment, check for proper operation.
End of Task