3-384. HOIST WINCH CABLE REPLACEMENT (Contd)
6.
Thread cable clevis (3) through forward boom sheaves (2) until only one part of cable (4) extends
from forward boom sheaves (2).
NOTE
Direct assistant to maintain tension on cable while crane hoist is
in operation.
7.
Continue to unwind cable (4) until screw (5) on hoist winch drum (6) is visible. Place hoist control in
NEUTRAL position and shut down hoist winch operation (TM 9-2320-272-10).
8.
Remove screw (5) and cable (4) from hole (7) in hoist winch drum (6).
9.
Install screw (6) in hoist winch drum (6) for storage.
10.
Pull cable (4) from boom (1).
1.
Thread cable end of cable (4) over forward boom sheaves (2) and through upper boom roller (9).
2.
Thread cable (4) around upper rear sheaves (8) and lower rear sheaves (10).
3.
Feed cable (4) under boom (1) to hoist winch drum (6).
4.
Remove screw (5), insert cable (4) through hole (7) in hoist winch drum (6), and install screw (5).