TM 9-2320-260-34-2
15-52. LIFTGATE LIFT FRAME MAINTENANCE (M820A2) (Contd)
e. Installation
N0TE
Two assistants will help with steps 1 through 3.
1. Aline lift frame (8) on main frame (l), and install shoulder shaft (3) and lift frame (8) on main
frame (1).
2. Manually raise lift frame (8) and aline with lifting cylinder rod (2).
3. Install lifting cylinder rod (2) on lift frame (8) with straight pin (14) and two new pins (4).
FOLLOW-ON TASKS:
Grease lubrication fittings (LO 9-2320-260-12).
15-205