TM 9-2320-392-10-2
M1083A1 SERIES PREVENTIVE MAINTENANCE
0103 00
CHECKS AND SERVICES (PMCS) - Continued
Table 18. Preventive Maintenance Checks and Services (PMCS) - During -
Model M1089A1 - Continued.
ITEM
INTERVAL
MAN-
ITEM
CREWMEMBER
EQUIPMENT
NO.
HOUR
TO BE
PROCEDURE
NOT READY/
CHECKED
AVAILABLE
OR
IF:
SERVICED
2
During
Material
Handling
Crane
(MHC)
Operation
WARNING
Do not operate Material Handling Crane (MHC) unless outriggers
are set up and MHC is level from side to side. Failure to comply may
result in serious injury or death to personnel.
Keep hands and feet clear of outriggers during operation. Failure to
comply may result in injury to personnel.
NOTE
Operate MHC control levers using even pressure. Moving lever slightly will
cause slow movement of MHC. Moving lever to full travel will cause faster
movement of MHC.
Check MHC controls one at a time for proper operation, obvious damage,
missing parts, binding, and looseness.
1. Set up outriggers
(4) (WP 0043 00).
0103 00-198