TM 9-2320-260-34
16-36. CONTROL VALVE BANK REPLACEMENT(M819) (Contd)
4.
Attach chain to control valve bank (2) and lifting device.
WARNING
All personnel must stand clear during lifting operations.
q
A swinging or shifting load may cause injury to personnel.
Z Ensure lifting capacity is greater than weight (165 lb (75 kg))
of control valve bank. Failure to do so may result in injury to
personnel or damage to equipment.
NOTE
Assistant will help with step 5.
Move control valve bank (2) from work area and install on bracket (5) in cab (3) with three screws (1)
5.
and new locknuts (4).
6.
Remove chain from control valve bank (2) and lifting device.
7.
Wrap male threads on four hoses (6) with antiseize tape.
8.
Connect seven tubes (12) and four hoses (6) to control valve bank (2).
Install clamp (24) on tubes (12) and studs (25) with two nuts (23).
9.
10.
Install plate panel (7) on brackets (26) with seven screws (8).
11.
Position wiper motor (9) on front panel (7) and install with seal (22), washer (21), lockwasher (20),
and two nuts (14) and (19).
Install adapter (18) and slotted nut (15) on shaft (13).
12.
Install wiper arm (16) on shaft (13) with screw (17).
13.
14.
Connect wire (10) to wiper motor (9) with screw (11).
16-222