TM 9-2320-260-34-2
15-36. CEILING AND FRAME MAINTENANCE (Contd)
NOTE
Perform step 4 if roof panel is to be installed (subtask b.).
Insulate entire structure with fibrous glass felt insulation.
Assistant will help with steps 4 and 5.
4. Lift ceiling panel (21) from wooden supports and position on ceiling frame (19).
5. Install ceiling panel (21) on ceiling frame (19) with one hundred forty-four new rivets (13) and
one hundred twenty-four new rivets (20).
6. Install two lifting brackets (22) on ceiling frame (21) with six new lockwashers (23), screws (12),
and nuts (18).
7. Install two new seals (14), moldings (15), and moldings (17) on ceiling frame (19) with one hundred
twenty-eight screws (16).