TM 9-2320-272-24-3
4-161. ELECTRICAL LOAD CENTER BOX MAINTENANCE (Contd)
4.
Install right 3-phase receptacle wiring harness (14) and three wires (18) in load center (3) and on
three circuit breakers (16) with three screws (17).
5.
Install wire (15) on neutral buss bar (10) with screw (19).
6.
Install right and left wiring harnesses (21) and (22) and wire (28) in load center (3) and on neutral
buss bar (10) with screw (29).
7.
Install two wires (24) and (26) on switch (25) with screws (23) and (27).
8.
Install wire (31) on relay (30) with screw (20).
4-785