TM 9-2320-272-24-2
4-4. POWER PLANT (M939/A1) REPLACEMENT (Contd)
Adjust chain hoist so engine and transmission are level for
placement on trestles.
9.
Lower engine (2) and transmission (3) onto engine transporter. Ensure two trestles of the
transporter are positioned under each side of front gearcase cover (5) and two trestles are positioned
under each end of flywheel (4).
Do not detach chain hoist from engine until engine is equally
distributed and is stable on transporter. An improperly supported
engine may cause injury to personnel. Mounting engine on
transport stand is solely temporary and is not intended as a
supporting requirement for engine repair. When repairing engine,
use repair stand.
10.
Disconnect adjustable chain hoist and utility chains from two engine lifting eyes (1).
4-52