TM 9-2320-260-34-2
16-19. INNER BOOM MAINTENANCE (M816)
THIS TASK COVERS:
d. Assembly
a. Removal
e. Installation
b. Disassembly
c. Cleaning and Inspection
lNITIAL SETUP
MATERIALS/PARTS (Contd)
APPLICABLE MODELS
M816
TOOLS
PERSONNEL REQUIRED
General mechanic's tool kit
Two
Chain sling and spreader bar
REFERENCES (TM)
TM 9-237
TM 9-2320-260-34P-2
Jack stand
EQUIPMENT CONDITION
Lifting device
Chain
Blocking
GENERAL SAFETY lNSTRUCTIONS
MATERIALS/PARTS
All personnel must stand clear during lifting
operations.
Ensure lifting capacity is greater than weight of
inner boom.
q The inner boom must be supported at all times to
prevent unbalancing of boom.
WARNING
All personnel must stand clear during lifting operations.
q
A swinging or shifting load may cause injury or death to
personnel.
Ensure lifting capacity is greater than weight (700 lb (318 kg))
of inner boom. Failure to do so may result in injury to personnel
or damage to equipment.
Attach chain and lifting device on inner boom (2).
1.
2.
Raise inner boom (2) to remove weight from pin (4).
Remove cotter pin (5) and pin (4) from extension cylinder (3) and boom (1). Discard cotter pin (5).
3.
Remove cotter pin (11) and grease fitting (15) from shaft (14). Discard cotter pin (11).
4.
Remove four screws (12), Iockwashers (13), cover (10), shaft (14), and inner boom roller (9) from
5.
boom (1). Discard Iockwashers (13).
Remove eight screws (8), Iockwashers (7), and two stop plates (6) from boom (1). Discard
6.
Iockwashers (7).
16-112