TM 9-2320-366-20-5
NOTE
All tiedowns are adjusted the same way. RH
front tiedown shown.
(17) Adjust tiedown (16) until slider (6) and stop (7) are
flush with side and end of S-280 shelter (24).
(18) Tighten two screws (10).
(19) Perform steps (17) and (18) on remaining
tiedowns.
NOTE
Four tiedown cables are installed the
same way. One tiedown cable shown.
Large end of S-280 tiedown ring points
toward cargo bed.
(20) Install hook (26) on upper S-280 shelter tiedown ring
(27).
Change 2
20-439