WARNIGN LIGHT WIRING REPLACEMENT cont'd
SLAVE RECEPTACLE REPLACEMENT cont'd

TM-9-2320-260-20 5-Ton 6x6 M809 Series Trucks (Diesel) Truck Cargo: 5-Ton 6x6 M813 (2320-00-050-8902) (EIC:BSB); Manual
Page Navigation
  542    543    544    545    546  547  548    549    550    551    552  
TM 9-2320-260-20
4-56. SLAVE RECEPTACLE REPLACEMENT
THIS TASK COVERS:
a. Removal
b. Installation
INITIAL SETUP
APPLICABLE MODELS
EQUIPMENT CONDITION
All
Parking brake set (TM 9-2320-260-10).
q
Battery ground cable disconnected (para. 4-48).
MATERIALS/PARTS
GENERAL SAFETY INSTRUCTIONS
Locknut
Six lockwashers
Remove all jewelry.
q
q When removing battery cables, disconnect ground
REFERENCES (TM)
cable first.
TM 9-2320-260-10
TM 9-2320-260-20P
WARNING
Do not remove slave receptacle before disconnecting battery
ground cables. If energized battery cables contact cab, a direct
short will result and may cause injury to personnel.
Remove all jewelry such as rings, dog tags, bracelets, etc. If
jewelry or disconnected battery mound cable contact battery
terminal, a direct short can result, causing instant heating of
tools, injury to personnel, tool damage, battery damage, or
battery explosion.
I
a. Removal
NOTE
Tag all wires for installation.
1.
Remove locknut (11), screw (19), ground cables (7), (12), and (20), and two lockwashers (9) from rear
battery box support hanger (13). Discard lockwashers (9) and locknut (11).
2. Remove nut (18), screw ( 14), and positive cables (15) and (17) from positive battery terminal (16).
3. Remove two screws (5), clamps (4) and (6), ground cable (7), and positive cable (17) from back cab
panel support (3).
4. Remove four nuts (21), lockwashers (22), and screws (1) from slave receptacle (2). Discard
lockwashers (21).
5. Remove two grommets (8) from cab floor (10) and pull slave receptacle (2) from cab (23).
I
b. Installation
1. Route ground cable (7) and positive cable (17) through cab (23) and cab floor (10).
2. Install two grommets (8) on ground cable (7) and positive cable (17) and install on cab floor (10).
3. Install slave receptacle (2) on cab (23) with four screws (1), new lockwashers (22), and nuts (21).
4. Install positive cables (15) and (17) on positive battery terminal (16) with screw (14) and nut (18).
5. Install ground cables (7), (12), and (20) on rear battery box support hanger (13) with screw (19), two
new lockwashers (9), and new locknut (11).
6. Install ground cable (7) and positive cable (17) on back cab panel support (3) with clamps (4) and (6)
and two screws (5).